City of Miami
City of Miami Certificate of Occupancy
A City of Miami Certificate of Occupancy confirms that qualifying new construction or a change of use has completed the required building process for occupancy. Before the City can issue the certificate, the permit must be final, required inspections must be approved and outstanding permit items must be completed. This page explains what is required, how to request the certificate and what to check when a Certificate of Occupancy is being held up.

What Is a City of Miami Certificate of Occupancy?
A Certificate of Occupancy, commonly called a CO, is issued by the City of Miami for qualifying projects after the required permit and inspection process has been completed.
The City of Miami uses a Certificate of Occupancy for:
- new construction
- changes of use
For example, changing a property from one type of use to another may require a new Certificate of Occupancy.
The City uses a Certificate of Completion for many remodels, renovations and shell buildings instead.
Your City of Miami permit record should identify which certificate is required for the project.
Certificate of Occupancy vs. Certificate of Completion
A Certificate of Occupancy and Certificate of Completion are related, but they are used for different types of projects.
The City of Miami states that a Certificate of Occupancy is generally issued for:
- new construction
- change of use
A Certificate of Completion is generally used for:
- remodels
- renovations
- shell buildings
The permit application in iBuild identifies whether the project requires a CO or CC.
This matters because requesting the wrong certificate can create unnecessary confusion at the end of the permit process.
What Is Required Before You Can Get a Certificate of Occupancy?
The City of Miami requires the permit to be final before a Certificate of Occupancy can be issued.
Before requesting the certificate, confirm:
- the permit number
- the complete property address
- the correct unit number, when applicable
- outstanding permit revisions have been completed
- contractor changes and other permit requests have been completed
- required final inspections have been approved
If one of these items is still open, the Certificate of Occupancy may not be ready to issue.
Final Inspections and the Certificate of Occupancy
Final inspections are one of the most important parts of the Certificate of Occupancy process.
A commercial project can involve several permit trades.
Depending on the project, final inspections may include:
- building
- electrical
- plumbing
- mechanical
- roofing
- Fire
- other required inspections
Each permit holder is responsible for requesting the inspections connected to that permit.
The City states that the required inspections must be completed to obtain the Certificate of Occupancy or Certificate of Completion.
How to Check City of Miami Inspection History
Inspection history can be reviewed through the City's iBuild system.
The City allows permit searches using information such as:
- permit number
- property address
- folio number
Reviewing the inspection history can help identify whether required finals have been completed or whether another inspection is still needed.
How to Request a City of Miami Certificate of Occupancy
Once the permit is final and the required inspections have been approved, the Certificate of Occupancy can be requested.
The City currently provides two ways to request a CO.
Request the Certificate Online
The City provides an online CO and CC request form.
After the City verifies the request, the certificate can be made available through iBuild.
The City currently states that a properly verified online request may be available to print within approximately 3 to 5 days.
Once available, log into iBuild and:
- Open Manage Permit.
- Search for the permit.
- Open the permit record.
- Select the Certificates tab.
- Print the available certificate.
Request the Certificate in Person
A CO can also be requested at:
Miami Riverside Center 444 SW 2nd Avenue 4th Floor Miami, FL 33130
The City states that when an in-person request is complete and the information is verified, the certificate can be provided at the Building Department.
How to Check Whether a Permit Is Final
A project can look finished while the permit record still shows an open requirement.
The City of Miami provides a Why Not Final feature in iBuild.
To check the permit:
- Log into iBuild.
- Go to Manage Application.
- Select Global Inquiry.
- Search using the process number, permit number or property address.
- Open the permit.
- Select Why Not Final.
This can help identify items that still need attention before the permit can reach final status.
Common issues can include:
- missing final inspections
- outstanding revisions
- incomplete permit requests
- permit completion issues
- unresolved trade permits
What If the Permit Is Expired?
An expired permit may need to be addressed before the project can reach final status.
The City of Miami has a Permit Completion process for expired permits.
Once approved, a Permit Completion can make the permit active again so the remaining work and inspections can be completed.
The process depends partly on the remaining cost of work.
What If the City Will Not Issue the Certificate of Occupancy?
Start with the permit record.
Check:
- whether the main permit is final
- whether all required final inspections passed
- whether related trade permits are complete
- whether revisions remain open
- whether a contractor change or other permit request is incomplete
- whether the permit is expired
- whether the address and unit information are correct
- whether additional City requirements remain open
The iBuild permit record and Why Not Final information can help identify what remains.
A Certificate of Occupancy issue is often connected to an unfinished permit requirement rather than the certificate request itself.
Certificate of Occupancy for Threshold Buildings
The City of Miami has an additional requirement for threshold buildings.
Before the final Certificate of Occupancy can be issued, the threshold engineer may need to submit a three-ring binder containing the final laboratory test results for the City's records.
Projects classified as threshold buildings should confirm the final documentation requirements before requesting the CO.
What Is a Temporary Certificate of Occupancy?
A Temporary Certificate of Occupancy, or TCO, may allow occupancy before every minor construction item is complete.
The City of Miami says a TCO is generally associated with new construction or a change of use.
Temporary certificates have expiration periods and require their own inspections and approval process.
A TCO is not the same as the final Certificate of Occupancy.
City of Miami Temporary Certificate of Occupancy Information
Certificate of Occupancy and Certificate of Use Are Different
A Certificate of Occupancy and Certificate of Use serve different purposes.
The Certificate of Occupancy relates to the building and completed construction or change of use.
A Certificate of Use relates to the business or activity operating at the location.
For a new building or a space that has undergone construction, the City of Miami says the applicable Certificate of Occupancy or Certificate of Completion may be required before obtaining a Certificate of Use.
These processes should be tracked separately.
Commercial Certificate of Occupancy in Miami
Certificate of Occupancy issues are especially important for commercial projects because several permits and inspections may need to reach final status.
This can affect projects such as:
- restaurants
- retail stores
- offices
- commercial buildouts
- tenant improvements
- franchise locations
- new commercial buildings
- changes of use
A project can have a main building permit plus electrical, plumbing, mechanical and other related permits.
The Certificate of Occupancy process becomes easier to manage when the team knows which permits are final and which items still need attention.
Common City of Miami Certificate of Occupancy Problems
Common issues include:
- missing final inspection
- failed final inspection
- open trade permit
- outstanding permit revision
- expired permit
- incomplete contractor change
- incorrect property address
- incorrect unit information
- permit not showing final
- missing threshold building records
- unresolved permit requirement
- wrong certificate type requested
Checking the permit record first can help narrow down what is preventing the certificate from being issued.
How Clear Property Records Helps
Clear Property Records helps commercial construction teams manage the permit steps leading to Certificate of Occupancy.
Support can include:
- permit record review
- permit status tracking
- inspection history review
- final inspection tracking
- open permit identification
- expired permit coordination
- outstanding requirement review
- permit correction coordination
- City follow-up
- Certificate of Occupancy coordination
- Permit Closure
Clear Property Records helps organize the process and identify what still needs attention.
The City of Miami controls inspections, permit status and issuance of the Certificate of Occupancy.
Service Highlights
- Certificate of Occupancy Coordination
- Permit Status Review
- Final Inspection Tracking
- Inspection History Review
- Outstanding Requirement Review
- Open Permit Review
- Expired Permit Coordination
- Permit Correction Coordination
- City Follow-Up
- Permit Closure
Common Problems
- Missing final inspection
- Failed final inspection
- Permit not final
- Open trade permit
- Outstanding permit revision
- Expired permit
- Incomplete contractor change
- Incorrect property address
- Incorrect unit information
- Missing threshold building records
- Unresolved permit requirement
- Certificate not available in iBuild
- Wrong certificate type requested
Frequently Asked Questions
What is a Certificate of Occupancy in the City of Miami?
A City of Miami Certificate of Occupancy is issued for qualifying new construction or a change of use after the required permit work, inspections and final permit requirements have been completed.
When does the City of Miami require a Certificate of Occupancy?
The City of Miami generally uses a Certificate of Occupancy for new construction and changes of use. Remodels, renovations and shell buildings generally use a Certificate of Completion instead. The permit record identifies which certificate applies.
What do I need before requesting a City of Miami Certificate of Occupancy?
Confirm the permit number and complete property address, make sure outstanding revisions or permit requests are complete, and verify that all required final inspections have been approved.
How do I request a Certificate of Occupancy in Miami?
The City of Miami allows CO requests through its online certificate request process or in person at the Building Department at Miami Riverside Center. After an approved online request, the certificate can be accessed through iBuild.
How long does a City of Miami Certificate of Occupancy request take?
The City currently states that when an online request is verified and correct, the certificate may be available to print through iBuild within approximately 3 to 5 days.
How can I tell why my City of Miami permit is not final?
Use the City of Miami iBuild system and open the Why Not Final information for the permit. This can help identify inspections, permit requests or other requirements that still need attention.
What is the difference between a Certificate of Occupancy and Certificate of Completion in Miami?
The City of Miami generally issues a Certificate of Occupancy for new construction or a change of use. A Certificate of Completion is generally used for remodels, renovations and shell buildings.
What is a Temporary Certificate of Occupancy in Miami?
A Temporary Certificate of Occupancy may allow occupancy before every minor construction item is complete. It requires separate inspections and City approval and is valid only for a limited period.
Is a Certificate of Occupancy the same as a Certificate of Use?
No. A Certificate of Occupancy relates to the building and its completed construction or change of use. A Certificate of Use relates to the business or activity operating at the property.
Can Clear Property Records help with a City of Miami Certificate of Occupancy?
Yes. Clear Property Records can help commercial project teams review permit status, track final inspections, identify outstanding permit requirements, coordinate permit issues and manage the steps leading to a Certificate of Occupancy.
Commercial Permits